Rehabilitation of the Road from Tumanyan to Bagratashen Border Checkpoint Recommenced

08-04-2019

Construction work of the second stage (Tumanyan-Bagratashen border checkpoint) of the M6, Vanadzor-Alaverdi-Georgia border Interstate Road Rehabilitation and Improvement Project has recommenced. The launch of the work was given in May, 2018.

Subgrade works, blasting work, construction of drainage pipelines, transportation of water pipelines are being carried out. Particular attention is paid to the road passing through Alaverdi. The representatives of the contractor assure that they will do their best to finish construction of sidewalks, installation of a new pedestrian base and bridge renovation in Alaverdi as soon as possible. They promise to start asphalt pavement in the given road section  in summer.

The length of the rehabilitated road is 51.74 km.

Construction work completion date is scheduled in the end of 2020.