The Road Section under the Guarantee Period has been Studied

08-05-2019

The engineering team of the "Transport Project Implementation Organization" SNCO visited the Vanadzor-Tumanyan section (38.45 km) of M6, Vanadzor-Alaverdi-Georgia border Interstate Road. The reconstruction work of this road section was completed on December 24, 2018 within the framework of the Interstate Road Rehabilitation and Improvement Project. After the completion of the road construction, the road is in one year Guarantee Period.

Meanwhile, the contractors carried out construction work in the mentioned roadway are obliged to eliminate the defects by their means, if necessary.

The engineers of the SNCO recorded that the reconstructed 38km section of the interstate highway was in good condition, only some defects were observed in the certain parts of the road.

The contractor will soon eliminate the defects.