Bagratashen New Bridge Alignment is in the Final Stage

14-02-2019

On February 13, 2019 Mrs. Astghik Sahakyan, Project Manager of Bagratashen border supervision crossing point new bridge construction, met with the representatives of the Tunnel Sadd Ariana company, which is the successful bidder for Bagratashen new bridge design and construction tender. On-going working issues were discussed.

The parties spoke about the construction plan and communication issues. They also touched upon the final version of Bagratashen new bridge alignment. It should be noted that the alignment was in the final stage. After confirmation the contractor would be able to complete the final detailed design of the bridge.

The contractor also presented the process of their joint work with the Georgian side.