Installation Of Curbs, Restoration Of Drainage System Is Carried Out

24-06-2019

The repair work of the M1-Hayrenyats-Tufashen-H 83 about 11km long road section has commenced. The restoration is carried out within the framework of the “Lifeline Roads Network Improvement Project: Additional Financing”. The Project is implemented by the funding of the RA government and the World Bank.

90% of earth work is completed till 19 June, 2019.

At present, the curbs installation and restoration of the drainage system are carried out.