THE SUBGRADE, ROAD PAVEMENT WORK IS BEING DONE ON THE KARMRASHEN-VOSKETAS-ZOVASAR ROAD

09-08-2018 8:42

Improvement work is being carried out on the road connecting the villages Karmrashen-Vosketas-Zovasar. The works are implemented within the framework of the “Lifeline Roads Network Improvement Project Additional Financing” by the "Transport Project Implementation Organization" SNCO.

Mr. Vazgen Petrosyan, Interim General Director of the "Transport Project Implementation Organization" SNCO and the representatives of the organization visited Aragatsotn region to get acquainted with the construction work.

The reconstruction of the road commenced in March 2018 and the completion date is scheduled in December 2018. The construction is carried out by "AAB Project" LLC. At the time of the site visit the contractor was doing earthwork, road pavement, sidewalk constructions.

The representatives of the "Transport Project Implementation Organization" SNCO recorded that some organizational omissions are observed during the restoration of the road. Particularly it has been mentioned that it is necessary to carry out the work in separate parts ensuring safe movement of local population.