Armenia Lifeline Road Network Improvement Project

  1. “Lifeline Roads Network Improvement Project” financed by the World Bank

 

The Project Loan Agreement between the Republic of Armenia and International Bank for Reconstruction and Development was signed on 11of February 2013. 
The Project Duration is till 30 June, 2017 (as per revision till 30 December 2019).
The Project Objective is to rehabilitate lifeline roads with overall length of approximately 170km during 2013-2016. 

The Project Progress: during 2013-2014 lifeline roads with total length of about 73.3km and in 2015 approximately 93km were rehabilitated and put into operation. Due to savings generated through the Project implementation it became possible to include additional road sections, as a result of which totally about 208.3km of roads will be rehabilitated within the framework of the Project, instead of initially planned 170 km.

 

  1. “Lifeline Roads Network Improvement Project: Additional Financing” financed by the World Bank is under preparation 

 

The Project Loan Agreement between the Republic of Armenia and International Bank for Reconstruction and Development was signed on 26 of August 2015. 
The Project Duration is till 30 December, 2019.
The Project Objective is to rehabilitate lifeline roads with total length of approximately 190km during 2016-2019. 
It is planned to rehabilitate seven lifeline roads during Year 1 of the Project implementation. 
The designs and Environmental Management Plans of rehabilitating road sections were developed.   

Armenia Lifeline Road Network Improvement Project

Completed project
Built in
Scheduled